Day 142 · Jubail-3 Utilities & Offsites — Package 4

KA
Daily Flash — Day 142

Jubail-3 Utilities & Offsites — Package 4 · SABIC (Fictional Demo) · Contract SBC-J3-EPC-04

% Complete
78%
Budget
On budget (–1.4% vs baseline)
Schedule
6 days behind (float 8 days)
Safety (LTI-free)
184 days
Progress trend · last 8 weeks
Manhours · by discipline
Key issues & watch-list
  • 01

    NCR-2884 (PMI mismatch, spool 5-P-2201) — material verification in progress with Delta Mechanical.

  • 02

    LLI slippage on Pkg 3 structural steel: vendor ETA W22 → W24. Recovery plan requested by EOB.

  • 03

    Coating crew productivity 62% of baseline on Line 42-P-4116 — mobilising second crew from Yanbu.

  • 04

    Hydro-test HT-04-11 punch clearance chased with Al-Rashid — target close-out by W23-T2.

Site photos · Day 142
Rack R-201 · cable pulling
Loop HT-04-11 · pre-hydro walk
Coating · Line 42-P-4116
Structural · beams 4B-102

All numbers reconciled from Primavera P6, SAP procurement, and QA/QC logs. Report must be signed by Deputy PM prior to circulation.