RFQ / TBA Comparison

ITB-P4-2024-11 · Package 4 — Utility Piping · 6 bidders

KA
Technical Bid Analysis · ITB-P4-2024-11
Auto-generated · pending TBA team review
VendorTech. CompliancePriceDeliveryCompliance flags
Arabian Pipes Manufacturing
ITB-P4-2024-11
References superseded rev — verify
96%
SAR 4.82M14 weeks Fully compliant
Gulf Steel & Fabrication
ITB-P4-2024-11
References superseded rev — verify
92%
SAR 4.39M16 weeks
Deviation on PWHT procedure vs SAES-W-011
Jubail Industrial Piping
ITB-P4-2024-11
References superseded rev — verify
88%
SAR 4.61M12 weeks
No 09CrCuSb material cert offered
Al-Khobar Metalworks
ITB-P4-2024-11
References superseded rev — verify
74%
SAR 4.12M18 weeks
Missing NDE plan
Sub-vendor list incomplete
PQR/WPS gaps
Riyadh Piping Solutions
ITB-P4-2024-11
References superseded rev — verify
90%
SAR 4.72M15 weeks
Payment terms deviate from GC-14
East Coast Fabricators
ITB-P4-2024-11
References superseded rev — verify
81%
SAR 4.26M13 weeks
Limited SABIC track record
One PQR outside range
ANCHOR AI recommendation
Advisory · TBA committee decides

Arabian Pipes Manufacturing offers the strongest compliance-to-cost ratio at 96% tech compliance and SAR 4.82M, with zero material deviations against SAES-L-105 and a validated PQR/WPS matrix.

Al-Khobar Metalworks is 15% cheaper but shows deviations that historically add 8–12 days of NCR rework in comparable Pkg 4 scopes.

Jubail Industrial Piping has the fastest lead time (12 weeks) — worth considering if procurement float on LLI slips further; however 09CrCuSb certification remains open.

Requires Deputy PM sign-off before circulation.