ANCHOR AI insight · advisory
Package 3 procurement is 9 days behind — projected to delay steel erection start by ~2 weeks, with knock-on impact to Pkg 4 tie-in windows. Recommend expediting LLI-201 (Gulf Steel & Fabrication) and reviewing float on Primavera activity A-3120.
Human review required · ANCHOR AI will not action expedite requests without Deputy PM approval.
Procurement status funnel
RFQ Issued
8
Bid Evaluation
5
PO Awarded
12
Fabrication
9
Delivery
4
Site
21
Long Lead Items
| Item | Vendor | Pkg | PO Status | Original | Forecast | Variance | Critical Path |
|---|---|---|---|---|---|---|---|
Primary Structural Steel — 620 T LLI-201 | Gulf Steel & Fabrication | Pkg 3 | Fabrication | 2026-05-18 | 2026-05-27 | +9 d | Yes |
Compressor Trains K-4101 A/B LLI-204 | MHI Middle East | Pkg 5 | Fabrication | 2026-07-02 | 2026-07-04 | +2 d | Yes |
HV Switchgear 33 kV LLI-207 | Siemens Energy KSA | Pkg 6 | Delivery | 2026-06-10 | 2026-06-08 | -2 d | No |
Storage Tank Plates — API 650 LLI-211 | Zamil Steel | Pkg 7 | PO Awarded | 2026-08-15 | 2026-08-29 | +14 d | Yes |
Fire & Gas Detectors (Package) LLI-214 | Honeywell KSA | Pkg 6 | Bid Evaluation | 2026-06-25 | 2026-07-01 | +6 d | No |
Cryogenic Valves 4"–24" LLI-218 | Emerson Automation | Pkg 5 | RFQ Issued | 2026-09-10 | 2026-09-10 | 0 d | No |
Cable Tray & Ladder — 14 km LLI-222 | Al-Fanar Cables | Pkg 6 | Site | 2026-04-30 | 2026-04-28 | -2 d | No |